Our build at Randolph Street got off to a great start with the 2021 Women Build Week. The women builders helped to frame the house. Since then a lot more work has gone on at the build. We have had some Team Builds that started the siding and public build days where our volunteers worked hard to get the siding hung.
While our volunteers worked on the siding our sub-contractors were busy getting their rough-in work completed. We've got our plumbing, mechanical and electrical in and the wall insulation hung. This week our contractors are hanging and finishing the wallboard. Next week it will be time to prime and paint!
We are looking at closing on the house with the Miller Family in around Labor Day.
Comments